Power cost

CATEGORIES
SPECIFICATIONS
Charge standards
Residential lighting 1)less than 1 KV ? Rmb 0.403/Kwh
2)over 1 KV ?Rmb 0.373/Kwh
Commercial and Non-residential Lighting 1)less than 1 KV Rmb 0.739/Kwh
2)over 1 KV Rmb 0.579/Kwh
Non-common industrial use (non-industrial use and common industrial use) 1)less than 1 KV Rmb 0.533/Kwh
2)1-10 KV Rmb 0.543/Kwh
3)over 35 KV Rmb 0.533/Kwh
Large Scale Industrial Use Basic charge as per transformer Max. demand to special enterprise Rmb12/KVA/month
Rmb 18/KWh/month
POWER CONSUMPTION CHARGE  
1)1-10 KV Rmb 0.381/Kwh
2)35 KV Rmb 0.371/Kwh
3)110 KV Rmb 0.361/Kwh
Sub-charge for electric power of erecting power transmission lines engineering (re-networking fund) 380V/220V Rmb 550/Kwh
10 KV Rmb 450/Kwh
35 KV Rmb 330/Kwh
110 KV Rmb 180/Kwh
Sub-charge for electric power engineering of laying cables 380KV/220V Rmb 1100/Kwh
10 KV Rmb 900/Kwh
35 KV Rmb 800/Kwh
110 KV Rmb 400/Kwh
 
Heat Supply Charge
Categories
Charging Standard
Industrial Use (for production purpose) Rmb 103/ton
Heating Use Factory Building Rmb 103/ton
Office Building Rmb 19.5/m2
Residential Building Rmb 13.5/m2
Business Use Rmb 25/m2
Facility fee
180000/ton
 
Tab Water Charge
Categories
Charge Standard
Industry Use Rmb 2.55/ton
Residential Use Rmb 1.2/ton
Institute Use Rmb 1.5/ton
Service Business Rmb 10/ton
Washing Rmb 15/ton
 
Telecommunications Charge
Types of Business
Standard of Charges (RMB)
Installing Charge Basic Monthly Rent
Telephone   Rmb 30(enterprise)
Rmb 18(resident)
Facsimile Rmb 300  
CHINANET Rmb 50-100 (opening fee) Rmb 4/hour (within 1-60 hours)
CHINAPAD   Installing charge for special line Rmb 2600/unit
Testing fee for switching network
Rmb 1000/unit (synchronous)
Rmb 400/unit (asynchronous)
Material cost: Rmb 158/unit
DDN   Charge of commissioning urban special line: Rmb 200/unit
 
Site-use Price
(1)land leasing price
Catalogue
Industrial
Commerce &trade, office building
Real estate
Basic price
Facility fee
Basic price
Facility fee
Basic price
Facility fee
In RMB/per mu
200,000
200,000
300,000 -350,000
100,000
100,000
Duration (year)
50
50
70
For information 1 mu=674.5 square meters
15 mu=1 ha
Different preferential prices are given according to the type of projects, source of the investments, technological contents and geographical location. The land should be available from plain land to the condition of road, water supply, electricity power, heat supply, drainage, natural gas supply, industrial steam supply and telecommunication
.
(2)Land-leading Rate for Standard buildings and office buildings
The price for standard buildings and office building is confirmed from Rmb 19-21 square meter according to the stories available, public facilities, communication condition and payment form and so on.
 
Labor Service Charge
Item
Standard and Proportion
Payment
Total Wages/salary Not less than 120% of the average wages of the employees of state-owned enterprise of the same trade in Baoding City Issue directly to employees in currency
Welfare Treatment during Employment According to the provision of the state, province and city on labor, insurance and welfare benefits for the employees in state-owned enterprises. Drawn out or actually disbursed according to the specified proportion
Old-age pension 20% of the total payment made by enterprises; 4% of the total payment of each employee made by employee himself. Paid every month by enterprise to Baoding High-tech zone branch of social Labor &Insurance Institute
Unemployment insurance funds 2% of the total payment made by enterprises; 1%of the total payment of each employee made by employee himself. Paid every month by enterprise to Baoding High-tech zone branch of social Labor & Insurance Institute
Industrial accident Insurance Payable by the enterprise equivalent to 0.4% of the total wages of employees. Paid every month by enterprise to Baoding High-tech zone branch of social Labor &Insurance Institute
Child-bearing Insurance funds Payable by the enterprise, equivalent to 0.9% of the total wages of employees. Paid every month by enterprise to Baoding High-tech zone branch of social Labor &Insurance Institute
Medical Benefit Funds Rmb 8 paid by each stuff worker every month.
Rmb 4 paid by each retired worker every month
Paid every month by enterprise to Baoding High-tech zone branch of social Labor &Insurance Institute
Housing accumulation Funds 10% of the total individual wages of staff and workers paid by staff workers themselves and their working units respectively. Paid every month by enterprise to the management center of Housing Funds Baoding City
 
Wastewater Discharge Charge

Wastewater discharged in conformity with national sanitation provision will be charged by RMB 0.15 per ton, and the wastewater over standard but allowed to discharge will be charged additionally by RMB 0.05 per ton.

Building Requirements

1) Fleer Area Index
Factory: 0.8-1
Residence:¡Ü1.5
Office and Commerce:1.5-2.5
2) Building Density¡Ü35%
3) Green Area Index¡İ30%
4) Height: Main buildings on the both sides along main roads are allowed to be more than 5 stories
5) Distance form the building ¡°red line¡± to the road ¡° red line¡±
15 m for main trunk roads, 6-10m for common roads
6) Enclosed walls
Fencing or railings may be built up in factory areas.
7) Earthquake intensity:7 degrees on the Richter Scale

Standards of Environment Protection
Discharge of Industrial Wastewater
Following ¡±Integrated Wastewater Discharge Standard¡±(GB8978-1996) of the People¡¯s Republic of China
.
Emission of Waster Gas, Smoke and Dust
Emission of air pollutants such as waste gas, smoke shall follow ¡°Integrated Emission Standard of air Pollutants¡±(GB16297-1996) of the People¡¯s Republic of China.

Noise control
Noise from industrial enterprise shall follow ¡°Standard of Noise at Boundary of Industrial Enterprises¡±(GB12348-90) of the People¡¯s Republic of China.
Noise from construction sites shall follow ¡°shtandard of Noise at construction Sites¡±(GB12523-90) of the People¡¯s Republic of china.